The plaintiff, Building Inspector, has lodged case against me for collection of his undue payment. The plaintiff had referred "Mercantile Law - Sale of Goods and Services" under Commercial list and sought the reason of claim as the contract with him includes only cost estimation and subject to change.
"Work done or materials provided by the plaintiff for the defendant at the defendant's request, pursuant to Rule 14.12 of the Uniform Civil Procedure Rules 2005 (NSW)."
I consider this as overcharging where intermediate invoice is more than 4 folds (400 times) the estimated cost for the service by adopting unfair practices to overcharge. Further the report is not delivered in the acceptable form. His timesheet includes site visit plus travel time 8.375 hour and report preparation for 53.95 hours. His work is related with producing the evidence report where he relied on visual inspection of the house and data collection using simple tools spirit level, tape, plumb bob, etc.
Please advise if I am obliged to pay the remaining about 3 times of the estimate for service which is not fit for purpose which is explained in below section. Please also suggest me if I would be able to recover the deposited amount as I had to engage another expert by terminating the contract. Before terminating the contract, i had sought his opinion to continue work as per estimate with 10 to 20% variation as acceptable condition.
Unsatisfactory professional misconduct
A.Service not provided with acceptable care by adhering to the best practices
1.Work undertaken by inspecting the site and then not engage time to prepare report till the report submission deadline date
2.Overspending time by doing out of scope work
3.Overspending time for data collection on minute details
4.Not notified for increase in cost estimation even after the site visit
5.Not notified for work already done beyond the deposited amount
6.Report missed the first deadline and was submitted on last day of submission date to NCAT without consideration reasonable time required for me to compile the report.
B.Professional Conduct not complying in accordance to NCAT Code of Conduct
1.Scott Schedule is prepared without proper scope of work where details on estimate cost calculation and work order for rectification work.
2.Technical content of the report where report is misleading
3.Error in report were not rectified and suggested rectification if reported by NCAT respondent parties.
4.Money order for rectification work on defects on the house is extremely high which is $494900. As an example, I have recently received the repair quote of around $22K plus 5K for material whereas the report cost in the report is in the figure of around $75K. Filling the silicon gap on one side of door is quoted $700.
C.Report is not concise.
The reader needs to devote lot of times as the report is not concise, content error, formatting error including wrong figure naming, figure caption, etc.
Chronological Order of Events
Quote was requested with Scope of Work to produce NCAT Expert Witness Report.
Estimate was given in the contract though detail information has been provided
Contract was accepted with 100 percent of payment of requested deposit amount.
The Expert inspected the site.
The Expert missed the deadline to submit the report to me and the report to NCAT. Deadline was extended.
The Expert provided the report on final day of submission deadline.
I had no option than to submit the report to NCAT on hardcopy and the respondent by email.
The Expert sent the invoice.
Terminated the contract as the expert is not willing to make amendment on estimated price
Engaged another expert for submitting the second report.
"Work done or materials provided by the plaintiff for the defendant at the defendant's request, pursuant to Rule 14.12 of the Uniform Civil Procedure Rules 2005 (NSW)."
I consider this as overcharging where intermediate invoice is more than 4 folds (400 times) the estimated cost for the service by adopting unfair practices to overcharge. Further the report is not delivered in the acceptable form. His timesheet includes site visit plus travel time 8.375 hour and report preparation for 53.95 hours. His work is related with producing the evidence report where he relied on visual inspection of the house and data collection using simple tools spirit level, tape, plumb bob, etc.
Please advise if I am obliged to pay the remaining about 3 times of the estimate for service which is not fit for purpose which is explained in below section. Please also suggest me if I would be able to recover the deposited amount as I had to engage another expert by terminating the contract. Before terminating the contract, i had sought his opinion to continue work as per estimate with 10 to 20% variation as acceptable condition.
Unsatisfactory professional misconduct
A.Service not provided with acceptable care by adhering to the best practices
1.Work undertaken by inspecting the site and then not engage time to prepare report till the report submission deadline date
2.Overspending time by doing out of scope work
3.Overspending time for data collection on minute details
4.Not notified for increase in cost estimation even after the site visit
5.Not notified for work already done beyond the deposited amount
6.Report missed the first deadline and was submitted on last day of submission date to NCAT without consideration reasonable time required for me to compile the report.
B.Professional Conduct not complying in accordance to NCAT Code of Conduct
1.Scott Schedule is prepared without proper scope of work where details on estimate cost calculation and work order for rectification work.
2.Technical content of the report where report is misleading
3.Error in report were not rectified and suggested rectification if reported by NCAT respondent parties.
4.Money order for rectification work on defects on the house is extremely high which is $494900. As an example, I have recently received the repair quote of around $22K plus 5K for material whereas the report cost in the report is in the figure of around $75K. Filling the silicon gap on one side of door is quoted $700.
C.Report is not concise.
The reader needs to devote lot of times as the report is not concise, content error, formatting error including wrong figure naming, figure caption, etc.
Chronological Order of Events
Quote was requested with Scope of Work to produce NCAT Expert Witness Report.
Estimate was given in the contract though detail information has been provided
Contract was accepted with 100 percent of payment of requested deposit amount.
The Expert inspected the site.
The Expert missed the deadline to submit the report to me and the report to NCAT. Deadline was extended.
The Expert provided the report on final day of submission deadline.
I had no option than to submit the report to NCAT on hardcopy and the respondent by email.
The Expert sent the invoice.
Terminated the contract as the expert is not willing to make amendment on estimated price
Engaged another expert for submitting the second report.